FISP Cycle 10 Sub-Cycles 10A, 10B and 10C: Which Filing Window Applies to Your Building

Published November 8, 2026

FISP Cycle 10 sub-cycle filing windows 10A, 10B and 10CA bar chart with years 2025 to 2029. Sub-cycle 10A, blocks ending in 4, 5, 6, 9: window opens 2/21/2025, deadline 2/21/2027. Sub-cycle 10B, blocks ending in 0, 7, 8: window opens 2/21/2026, deadline 2/21/2028. Sub-cycle 10C, blocks ending in 1, 2, 3: window opens 2/21/2027, deadline 2/21/2029.20252026202720282029Ticks mark February 21Sub-cycle 10ABlock ends in4, 5, 6, 9Window opens2/21/2025Deadline2/21/2027Sub-cycle 10BBlock ends in0, 7, 8Window opens2/21/2026Deadline2/21/2028Sub-cycle 10CBlock ends in1, 2, 3Window opens2/21/2027Deadline2/21/2029
Cycle 10 filing windows by the last digit of the tax block. Sub-cycle 10A (blocks ending in 4, 5, 6, 9): window opens 2/21/2025, deadline 2/21/2027. Sub-cycle 10B (0, 7, 8): opens 2/21/2026, deadline 2/21/2028. Sub-cycle 10C (1, 2, 3): opens 2/21/2027, deadline 2/21/2029. Dates are from DOB's Cycle 10 diagram and 1 RCNY 103-04.

Which Cycle 10 filing window applies to which building?

Your building’s sub-cycle comes from the last digit of its tax block number.

Sub-cycle 10A is for blocks ending in 4, 5, 6 or 9. The window runs from February 21, 2025 to February 21, 2027.

Sub-cycle 10B is for blocks ending in 0, 7 or 8. The window runs from February 21, 2026 to February 21, 2028.

Sub-cycle 10C is for blocks ending in 1, 2 or 3. The window runs from February 21, 2027 to February 21, 2029.

As of November 8, 2026, 10A owners have 105 days left before their window closes.

Sub-cycle Block ends in Window opens Deadline Status on Nov 8, 2026
10A 4, 5, 6, 9 2/21/2025 2/21/2027 Open, 105 days left
10B 0, 7, 8 2/21/2026 2/21/2028 Open
10C 1, 2, 3 2/21/2027 2/21/2029 Opens 2/21/2027

The opening dates match the dates our earlier Cycle 10 guide lists. This table adds the closing dates, and those are the dates penalties key off.

Where do these dates come from?

They come from DOB’s Cycle 10 Sub-Cycle Diagram and 1 RCNY 103-04, and the two line up.

DOB’s diagram shows the five-year cycle period from 2/21/2025 to 2/20/2030. It also shows the sub-cycle openings on 2/21/2025, 2/21/2026 and 2/21/2027, with deadlines of 2/21/2027, 2/21/2028 and 2/21/2029.

The rule text in 1 RCNY 103-04(c)(4)(v) says the same thing in formula form. For blocks ending in 4, 5, 6 or 9, the window starts February 21 of years ending in 0 and 5 and ends February 21 of years ending in 2 and 7. The 0/7/8 group starts one year later. The 1/2/3 group starts two years later.

The cycle runs five years, so the windows overlap. DOB says the sub-cycles were added to make it easier for owners to hire qualified professionals and contractors.

How do I find my block number?

Use DOB’s Facade & Local Law page and its FISP Universe Map. The map lists subject facades and their filing cycle.

DOB also says the list is based on City records and does not replace the owner’s duty to confirm.

The step-by-step lookup is in our Cycle 10 guide, so it is not repeated here.

Which buildings are subject at all? Buildings greater than six stories, except for wall sections less than twelve inches from an adjacent building’s exterior wall. A building with six stories above grade plus a cellar is also covered when more than half the cellar’s height is above the adjacent ground level at any exterior wall.

How should I time the inspection inside the window?

The filing window is only one date range. Three other clocks in 103-04 matter too:

  • 60 days. A report must be filed within 60 days of the date the QEWI completed the critical examination (the final inspection). Miss that and a new critical examination is required.
  • One year. A report may not be filed more than one year after completion of the close-up inspection.
  • 45 days. If DOB rejects a report, a revised one is due within 45 days, and the original file date stops being valid. After two rejections a new initial filing fee applies.

Access work is part of this too. Physical examinations from scaffolding or another observation platform must occur at intervals of not more than 60 feet, with at least one examination for a facade under 60 feet and one more for every additional 60 feet, along a path from grade to the top of each wall facing a public right-of-way.

DOB’s rule also says drones and high-resolution photography do not eliminate the close-up requirement. See facade access methods compared for what each access option involves.

The window is a filing deadline, not a repair deadline. But if a report comes back Unsafe, the 90-day correction clock starts at submission, so a filing made in the last weeks of a window leaves repairs on a short schedule. Our owner timeline lays out that sequence.

What special cases change the window?

  • New buildings. Under 103-04 the initial report is due five years after the first Temporary Certificate of Occupancy or Certificate of Occupancy, if that date falls inside the applicable window. If not, it is due in the window for the next cycle. Local Law 49 changes the statute’s timing for a new building’s initial examination from the fifth to the eighth year after the exterior wall is erected, effective October 1, 2026, and the rule text has not been updated to match.
  • Multi-building complexes. If contiguous zoning lots under single ownership or management hold at least two buildings over six stories that fall in different windows, the owner may file each separately or pick one window for all. Choosing one requires telling DOB 180 days before the end of the assigned window, and the choice binds for the duration of ownership.
  • Overdue owners. The “No Report Filed” early-filing exception above applies from Cycle 10, with penalties paid on filing.

Does Local Law 49 of 2025 move any of this?

Local Law 49 changed the statute so DOB can set intervals of 6 to 12 years by rule, effective October 1, 2026.

As of November 8, 2026, the rule text still defines a five-year report filing cycle and the same staggered windows listed above. DOB’s Facade & Local Law page also still states that facade inspections are required every five years.

Until DOB publishes a different rule, plan to these dates. Our Local Law 49 guide tracks what the statute does and does not do, and the DOB recommendations report breakdown covers the study behind it.

What happens after the window if the report found problems?

If the rating is SWARMP or Unsafe, filing is only the start.

Altius CM is the repair contractor in that sequence, working with the owner’s QEWI. The QEWI inspects and files.

If your building is in 10A and facade work is likely, start with facade repair and replacement, and see the Local Law 11 overview for the program background.

Sources

Last verified: November 8, 2026. Windows are from DOB’s published diagram and rule; confirm your own building’s cycle in DOB NOW: Safety. This is general information, not legal advice.

Frequently asked questions

What are the Cycle 10 filing deadlines for 10A, 10B and 10C?

DOB's Cycle 10 diagram shows deadlines of 2/21/2027 for 10A, 2/21/2028 for 10B, and 2/21/2029 for 10C. The windows open 2/21/2025, 2/21/2026, and 2/21/2027, so each sub-cycle has a two-year window, as 1 RCNY 103-04 defines a filing window.

How do I know whether my building is 10A, 10B or 10C?

The last digit of the building's block number decides it. Blocks ending in 4, 5, 6, or 9 are 10A. Blocks ending in 0, 7, or 8 are 10B. Blocks ending in 1, 2, or 3 are 10C. DOB also publishes a FISP Universe Map, and states that it is ultimately the owner's responsibility to identify whether the building is subject to the program.

Do I have to wait for my window to open before filing?

Generally the window governs when a report may be filed without penalty. The rule makes one exception, starting in Cycle 10: owners whose most recent status is 'No Report Filed' may file before their window starts, provided all applicable civil penalties are paid at the time of filing.

What happens the day after my window closes?

Penalties apply after the filing period ends. The rule sets a $1,000 per month late filing penalty that starts the day after the deadline and runs until an acceptable initial report is filed, and a $5,000 per year penalty for failing to file.

Does Local Law 49 of 2025 change these windows?

Not on the rule text DOB posts today. Local Law 49 lets DOB set inspection intervals of 6 to 12 years by rule, effective October 1, 2026, but the 1 RCNY 103-04 text checked on November 8, 2026 still describes a five-year report filing cycle and the same staggered windows. Keep to the published Cycle 10 dates.