FISP Ratings Explained: What Safe, SWARMP and Unsafe Require, and By When

Published November 8, 2026

How a FISP filing gets its building rating: Unsafe, SWARMP or SafeA decision flow. If there is at least one unsafe condition, the building is Unsafe: public protection right away and correction within 90 days from when the report is submitted to DOB. If not, and there is at least one SWARMP condition, the building is SWARMP: a repair date written into the report that cannot be less than one year out. Otherwise, with no Unsafe or SWARMP conditions, the building is Safe, with no repair deadline.The whole filing follows the worstcondition in the reportAt least oneunsafeconditionUnsafepublic protectionright awaycorrection within90 days from whenthe report issubmitted to DOBYesNoAt least oneSWARMPconditionSWARMPa repair datewritten into thereportthat date cannotbe less than oneyear outYesNoSafeno Unsafe or SWARMP conditionsno repair deadline
The rating follows the worst condition in the report. At least one unsafe condition: Unsafe, with public protection right away and correction within 90 days from when the report is submitted to DOB. Otherwise, at least one SWARMP condition: SWARMP, with a repair date written into the report that cannot be less than one year out. No Unsafe or SWARMP conditions: Safe, with no repair deadline.

What does each FISP rating require, and by when?

The whole filing follows the worst condition in the report.

If there are no Unsafe or SWARMP conditions, the building is Safe. If there is at least one SWARMP condition and no Unsafe condition, the building is SWARMP. If there is at least one Unsafe condition, the building is Unsafe.

The deadlines are very different. A Safe filing has no repair deadline. A SWARMP filing gets a repair date written into the report, and that date cannot be less than one year out. An Unsafe filing requires public protection right away and correction within 90 days from when the report is submitted to DOB.

This article stays with the rule text in 1 RCNY 103-04. If you want the report form broken down, see how to read a FISP report. For filing windows, see the Cycle 10 guide and our sub-cycle window breakdown.

How does the inspector decide which rating the building gets?

The Qualified Exterior Wall Inspector (QEWI) classifies each condition as safe, unsafe or SWARMP. Then the building rating follows the rule:

  • No unsafe and no SWARMP conditions: the building is Safe.
  • At least one unsafe condition: the building is Unsafe.
  • At least one SWARMP condition and no unsafe ones: the building is SWARMP.

DOB adds one practical limit on its Facade & Local Law page. Buildings with ongoing construction may not be designated Safe.

A Safe report still has to include color photos of at least three typical conditions. Every report also has to state the facade’s water-tightness.

What does a Safe rating require?

Under the rule, a safe condition does not require repair or maintenance to sustain the structural integrity of the exterior, and will not become unsafe during the next five years.

There is no repair deadline tied to a Safe rating. The job is to file within your window and, in the next cycle, have the inspector certify that anything flagged earlier was corrected.

What does a SWARMP rating require, and what is the deadline?

SWARMP means safe at the time of inspection, but needing repairs or maintenance during the next five years to keep the condition from becoming unsafe. The rule also says the timing cannot be less than one year out.

The report has to name a real date, in MM/DD/YYYY form, by which the work must be performed. The rule does not accept a period shorter than one year. It also does not accept wording like “ASAP” or “immediately.”

Under 103-04(c)(6), the owner must complete the recommended actions within the inspector’s time frame and notify DOB of any deviation. If the time frame changes, that requires a subsequent report with supporting documents from the QEWI.

There are also two hard limits in the rule:

  1. A report may not describe the same condition at the same location as SWARMP in two consecutive cycles.
  2. At the next inspection, the QEWI must certify each condition previously reported as needing repair. If one was not corrected, it must be reported as Unsafe.

What does an Unsafe rating require, and how fast?

Unsafe means a condition hazardous to persons or property.

Once the report is filed, public protection is required immediately. The QEWI must notify DOB and the owner on discovering an unsafe condition and recommend the type and location of protection. DOB’s page lists a sidewalk shed, a fence or structural netting as acceptable forms, and all require DOB permits.

The repair deadline is 90 days from submission of the report. That is the rule in 103-04(c)(5).

If the repair takes longer than 90 days of work, the QEWI must recommend a longer time frame in the report, up to five years. The owner is then responsible for completing the work within that time. The mechanics of the extension track are laid out in our owner timeline.

After the repairs are completed, the QEWI must inspect within two weeks and file an amended report. The owner must get permit sign-offs. DOB’s page gives a combined limit of 104 days from the original filing date. If the repairs cannot be finished and the amended report filed by then, an extension must be requested.

There is one wrinkle in the wording. The rule’s definition of an unsafe condition says it “requires repair within one (1) year of completion of critical examinations),” but the operative deadline in 103-04(c)(5) is 90 days from submission. Plan around the 90 days.

What do missed deadlines cost?

The figures below are from 103-04(d) and DOB’s Facade Fees & Penalties page.

Situation Penalty
Late initial filing $1,000 per month, from the day after the window closes until an acceptable report is filed
Failure to file $5,000 per year after the window ends
SWARMP condition not corrected, refiled as Unsafe $2,000
Unsafe condition not corrected $1,000 per month, plus a shed charge in years 2 to 5

For Unsafe conditions, the base penalty is $1,000 per month every year. Starting in year 2, DOB adds a charge per linear foot of shed per month: $10 in year 2, $20 in year 3, $30 in year 4, $40 in year 5.

Using that table, a building in year 3 with 100 linear feet of shed owes $1,000 plus $2,000, for a total of $3,000 per month.

The penalty continues until DOB receives an acceptable amended report showing the conditions corrected, the shed removed and associated permits signed off, or until an extension is granted.

An owner can challenge a penalty in writing within 30 days of service by providing proof of compliance, such as the accepted report or approved extension requests.

Where does repair work fit between the rating and the amended report?

The QEWI inspects, classifies, files and certifies. The owner hires the repair contractor to do the work identified in the report.

Altius CM is a repair contractor. It performs the repairs the owner contracts for and coordinates access and sequencing with the owner’s QEWI. It does not inspect or sign off.

Sometimes that scope is big. The 529 West 42nd Street FISP 9 restoration, a $3M+ contract in progress, includes full parapet reconstruction, steel lintel replacement and shelf angle refurbishment. See facade repair and replacement and parapet repair for what that work covers, and budgeting facade restoration for how scope grows once a wall is opened up.

If an Unsafe filing leads to a shed, that shed also falls under the newer rules covered in our Local Law 48 guide.

Sources

Last verified: November 8, 2026. Rule text and DOB pages change; confirm your building’s status and deadlines in DOB NOW: Safety and with your QEWI. This is general information, not legal advice.

Frequently asked questions

Does one Unsafe condition make the whole building Unsafe?

Yes. Under 1 RCNY 103-04, if there is at least one unsafe condition the building is classified as Unsafe. If there are no unsafe conditions but at least one SWARMP condition, the building is SWARMP. Only a report with neither is classified Safe.

How long do I have to repair a SWARMP condition?

The inspector writes a date into the report, in MM/DD/YYYY form, by which the work must be performed. The rule does not accept a time frame shorter than one year, or wording such as 'ASAP' or 'immediately'. The SWARMP definition looks out five years, so the date falls between one and five years from the report.

What happens if a SWARMP condition is not fixed by the next cycle?

The inspector must report it as Unsafe. The rule also bars filing the same condition at the same location as SWARMP in two consecutive cycles. The owner of a building that files the uncorrected condition as Unsafe is liable for a $2,000 civil penalty under the rule.

Can the 90-day Unsafe deadline be extended?

Yes, but only on the inspector's application. The Commissioner may grant up to 90 more days when the application includes notice that the site is protected, a copy of the repair contract, the inspector's time estimate, a statement of permit requirements, a notarized owner affidavit and a fee. The rule states that financial considerations are not accepted as a reason.

When can the sidewalk shed come down after an Unsafe filing?

Protective measures stay in place until DOB accepts the amended report. The inspector may ask to remove the shed earlier by submitting a signed and sealed statement that the conditions were corrected and the shed is no longer required. Permission is at the Commissioner's sole discretion.